The following is the tentative schedule for the new 610 design-build construction project:
| Design: |
Fall 2009 - March 2010 |
| Noisewalls: |
Fall 2009, begin again March - August 2010 |
| Pedestrian Bridge: |
Fall 2009 - June 2010 |
| Hemlock Lane: |
Fall 2009 - June 2010 |
| Revere Lane: |
Fall 2009 - June 2010 |
| Sanitary Sewer: |
Fall 2009 - August 2010 |
| Zachary Lane: |
April 2010 - June 2011 |
| Jefferson Highway: |
June 2010 - September 2010 |
| Highway 169: |
May 2010 - November 2010 |
| |
|